Re­nour­ishment project hits roadblock, 9 miles of Pinellas beaches in limbo

PINELLAS COUNTY, Fla. — A renourishment project aimed at protecting and preserving 9 miles of Pinellas County beaches has hit a roadblock.

Every six years since the late 1980s, more than 1 million cubic yards of sand has been moved into the nine-mile stretch of beach from the Crescent Beach Club area in Clearwater to the north end of Redington Beach.

John Bishop, Coastal Management Coordinator for Pinellas County, said that stretch of beach didn't exist before the renourishment projects began roughly 30 years ago. For the most part, the ocean went up all the way to the seawall, leaving only a small strip of soggy coastline, he said.

"All of these dunes and beach are manmade, this isn't a natural beach," Bishop said. "It may look natural, but it wasn't here 30 years ago."

The next renourishment project was slated for 2024 but won't be happening on schedule, he said.

The Army Corp of Engineers is now requiring that Pinellas County get all beachfront property owners to sign easements so federal dollars can be used. After working for roughly a year to obtain all of the signatures, the county only has 48% of them.

The easements are from the seawall to the erosion control line, which, in many cases on the stretch, is where the dunes begin.

"Until we solve this easement issue, this project probably isn't going to go anywhere," Bishop said.